Installing Primary AC Power, Continued
Circuit Breaker
The circuit breaker should have the correct ampere rating, number of poles, and rated for the area that it
will be installed. The circuit breaker must be installed in close proximity to the Maxum II so it is easily
accessible to the service technician for turning power off to perform maintenance functions or for safety
purposes. In addition, the circuit breaker must be labeled as the disconnecting device for the Maxum II.
CAUTION All AC power (Mains) wiring shall be in accordance with all applicable codes.
Conduit
The AC primary power rigid and explosion proof conduit must be ½” (1.26 cm) minimum diameter. The
conduit end, which terminates at the Enclosure, must be equipped with an explosion proof seal. The
conduit terminates at the Enclosure opening located on the top left side.
It is recommended that a conduit hub be used to securely connect the conduit to the EC Enclosure. The
conduit hub type used must meet the electrical codes for the area of installation.
Specific Application Information
Application Drawing Package, Block Diagram Utility Connections sheet and Arrangement
Drawing Electronics Controller sheet.
CE Conformance Requirements page
17.
Power Entry
The primary AC (Mains) power can be routed to the Maxum II through side or top access plates. The
plates can be punched to accommodate conduit or cable gland connectors.
Cable Gland
Removable
Access Plate
Figure 2-2: AC Power Entry Through Top Access Plate
Power Connections
The AC input power connection is made to a removable green connector (TB1) located on the upper left-
hand side of the Power Entry Control Module (PECM). Refer to Figure 2-3. The bottom connector
assembly is hardwired to the (PECM) circuit board and is non-removable. TB2 is used if the analyzer has
a second high wattage heater. TB10 is the power source for the Maxum II electronics, exclusive of the
heaters.